BREEAM Drying space
Contents |
[edit] Aim and benefits
The aim of this credit is to allow residents a space to dry clothes which is not energy intensive (tumble drying), and does not cause damp in the home.
This issue offers the following potential benefits to end users and clients:
- Reduced energy consumption / energy bills;
- In multi-residential accomodation, allows for space saving / lifestyle options in dwellings through centralised facilities.
[edit] When to consider
During RIBA Stage 2, establish whether drying space in individual residences is more appropriate, or a communal drying area.
If a communal drying area is suggested, allow sufficient space in the concept design.
Drying spaces in residences can be considered relatively late on in the process, around RIBA Stage 3 to 4, as there are very space efficient methods of achieving the credit, so premium space is not necessarily required.
[edit] Step by step guidance
Awaiting content
[edit] Questions to ask while seeking compliance
Awaiting content
[edit] Tools and resources
Ideas for alternative styles of drying rack to typical solution:
[edit] Tips and best practice
Often clients do not particularly want to include drying space. This is because the standard solution (a pull out rack over a bath) isn't the most attractive of options. It may be that you need to remind the client of what the purpose of this credit is, and perhaps suggest alternative drying rack options which still meet the aims of the credit but meet the aesthetic of the property better.
[edit] Typical evidence
[edit] Design Stage
[edit] Individual drying space:
- Architectural drawing(s) showing location of drying space
- Architectural specification detailing manufacturer of drying rack
- Manufacturer's data stating length of drying line
- [If internal] M&E specification stating required heating and ventilation for room with drying rack in
- [If external] details of posts/footings/fixings
[edit] Communal drying space:
- Architectural drawing(s) showing location of drying space
- Architectural specification detailing manufacturer of drying rack
- Manufacturer's data stating length of drying line
- [If internal] Architectural (or M&E) specification detailing access controls
- [If internal] M&E specification stating required heating and ventilation for room with drying rack in
- [If external] Details of how external space is accessible only to residents (marked up drawing, access statement)
- [If external] details of posts/footings/fixings
[edit] Post Construction Stage
- As per design stage, plus
- Site Inspection Report with photographs confirming
- Location of drying space
- Sufficient length
- Access controls
- Permanent fixing
- Heating and ventilation provision
[edit] Applicable Schemes
The guidelines collated in this ISD aim to support sustainable best practice in the topic described. This issue may apply in multiple BREEAM schemes covering different stages in the life of a building, different building types and different year versions. Some content may be generic but scheme nuances should also be taken into account. Refer to the comments below and related articles to this one to understand these nuances. See this document for further guidelines.
- Written to cover UK New Construction 2014
BRE Global does not endorse any of the content posted and use of the content will not guarantee the meeting of certification criteria.
--Tom Blois-Brooke 16:45, 01 Jul 2019 (BST)
--Multiple Author Article 21:59, 21 Apr 2018 (BST)
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.